This article is about How to Add, Delete, or Edit Activities in Primavera P6. In this article we are trying to provide you good information about How to Add, Delete, or Edit Activities in Primavera P6. We have arranged the information in this post to make you understand it easily. We hope that you can understand it well. Please check the information below.

How to Add, Delete, or Edit Activities in Primavera P6

00 How to Add, Delete, or Edit Activities in Primavera P6

Tip: To add activities while working with several projects on the Activities page, you have to group activities by Project or WBS. When working with one project, you are able to add activities regardless of grouping options.

To add an activity

  1. Select the location in the project structure where you need to add the activity. The new activity will be added straightly beneath the element you select.

For example, to add an activity to a project without assigning it to a specific WBS element, select the project row (when the view is grouped by project). To add an activity to a WBS element within a project, select the WBS row. To add an activity immediately beneath another activity, select the activity.

Sponsored Links :
  1. Click icon to add an activity (Insert), or right-click on the element and choose Add activity.

If data is grouped, the new activity inherits the value of the grouping field, or fields, if multiple grouping levels are applied. For example, if grouped by Activity Status and you add an activity to the In Progress group, the new activity is designated as in progress with an actual start date.

When data is grouped by a field other than WBS or Project, new activities are assigned to the project level, or root node, of the WBS.

To delete one or more activities, select them and click icon to delete a project element (Delete).

To edit an activity name/ID or its associated data, navigate to the appropriate field cell, double-click, then type your changes.

Note that you can also edit activity data through the details page. To access details, in the toolbar, click icon to represent activity details.

So that is all about How to Add, Delete, or Edit Activities in Primavera P6. We think that it is good information about How to Add, Delete, or Edit Activities in Primavera P6. We hope that this information is useful for you. Please share if you think that this information can be useful for others. If you need more article related to How to Add, Delete, or Edit Activities in Primavera P6 you can simply subscribe this blog. Thanks for visiting and have a nice browsing. source: oracle.com