How to Calculate Critical Float Path in Primavera P6

Sponsored Links :

This article is about How to Calculate Critical Float Path in Primavera P6. In this article we are trying to provide you good information about How to Calculate Critical Float Path in Primavera P6. We have arranged the information in this post to make you understand it easily. We hope that you can understand it well. Please check the information below.

How to Calculate Critical Float Path in Primavera P6

00 How to Calculate Critical Float Path in Primavera P6

To calculate multiple critical float paths for all open projects from the Projects > Activities page

  1. Open the project or group of projects you want to work with in the Projects section.
  2. Click Activities on the Projects toolbar to display the Activities page.
  3. On the Activities page, click Schedule on the Activities toolbar.
  4. In the Schedule Project dialog box, click Scheduling Options, then click the Advanced tab.

When you set scheduling options from the Activities page, your selections apply to all open projects.

  1. Mark the Calculate multiple float paths option.
  2. Choose to calculate multiple paths using Total Float or Free Float.
  3. In the Display multiple float paths ending with activity field, click Assign to choose the activity you want the float paths to end on. You can choose any activity; however, typically this activity is a milestone or some other major activity in the project schedule.
  4. Specify the number of float paths you want to calculate. Type a low number (10 or less) to optimize performance.
  5. Click Close.

To calculate multiple critical float paths for a project from the Projects > Tools page

  1. Open the project or group of projects you want to work with in the Projects section.
  2. Click Tools page on the Projects toolbar to display the Tools page.
  3. If multiple projects are open, select the project you want to work with from the Select Project list.

Note: If a single project is open, the Select Project list does not appear. When multiple projects are open, the Select Project box lists all open projects you have rights to access. Any action you perform, and all data that appears on the page, applies to the selected project only.

Sponsored Links :
  1. Click Scheduling Options, then click the Advanced tab.
  2. Mark the Calculate multiple float paths option.
  3. Choose to calculate multiple paths using Total Float or Free Float.
  4. In the Display multiple float paths ending with activity field, click Assign to choose the activity you want the float paths to end on. You can choose any activity; however, typically this activity is a milestone or some other major activity in the project schedule.
  5. Specify the number of float paths you want to calculate. Type a low number (10 or less) to optimize performance.
  6. Click Close.

Notes:

  • If you choose to calculate multiple paths using Total Float, based on the activity you want the paths to end on, P6 Web Access determines which predecessor activity has the most critical Relationship Total Float on the backward pass. This process repeats until an activity is reached that has no relationship. The forward pass begins from this activity and the successor activity that has the most critical Relationship Successor Total Float is determined. This process repeats until an activity is reached that has no relationship. These activities are assigned a Float Path value of 1 (the most critical float path) and the process begins again until the specified number of paths are calculated.
  • If you choose to calculate multiple paths using Free Float, the most critical path will be identical to the critical path that is derived when you choose to define critical activities as Longest Path in the General tab of the Schedule Options dialog box. In a multi-calendar project, the longest path is calculated by identifying the activities that have an early finish equal to the latest calculated early finish for the project and tracing all driving relationships for those activities back to the project start date.

So that is all about How to Calculate Critical Float Path in Primavera P6. We think that it is good information about How to Calculate Critical Float Path in Primavera P6. We hope that this information is useful for you. Please share if you think that this information can be useful for others. If you need more article related to How to Calculate Critical Float Path in Primavera P6 you can simply subscribe this blog. Thanks for visiting and have a nice browsing. source: oracle.com