How to Determine Resource Rate in Primavera P6

Sponsored Links :

This article is about How to Determine Resource Rate in Primavera P6. In this article we are trying to provide you good information about How to Determine Resource Rate in Primavera P6. We have arranged the information in this post to make you understand it easily. We hope that you can understand it well. Please check the information below.

How to Determine Resource Rate in Primavera P6

00 how to determine resource rate in primavera p6

If you have the required privileges, you can set the rate for an assignment on the Activity Resource Details page.

Display Activity Resource Details

Do one of the following:

    • in a workspace portlet, click on the activity name.
    • open the project or project group you want to work with, then click Activities on the Projects toolbar to display the Projects > Activities page. Select the activity in the Activity Table, then click icon to display details on the Activities toolbar. In the Activity Details form, expand the Resources section, if necessary.
    • in the Activity Table, right-click and select Edit Assignments to open the Assignments dialog box, in which you can assign a new resource or modify the rate of a selected resource.

The layout you see depends on a combination of administrative configurations and your preference settings. If Resource details do not appear, edit your preferences to add them.

Specify the rate

  1. Click the resource or role name.
  2. To calculate assignment costs based on the rate you select, mark the Calc Cost from Units checkbox.

When you save your changes, costs for the assignment are recalculated based on the new rate: (Cost = Units * Price/Unit). If this option is not set, you can manually record costs.

Sponsored Links :
  1. To set the price/unit based on the rate type and price/unit combinations defined for the role or resource, modify the Rate Type and/or Rate Source fields.

To manually specify a price/unit, in the Rate Source field, choose Override. Then, type a value in the Price/Unit field.

  1. Click Save.

Rates Overview

The Rate Type and Rate Source of an activity can be used to determine the price/unit, or rate, applied to an activity resource or role assignment.

Rate Types

A Rate Type is simply a narrative designation for a specific price-per-unit of work. Up to five Rate Types can be defined in the Project Management module. Your P6 administrator may or may not have modified the default Rate Type names, which are Price/Unit, Price/Unit2, and so on. For example, you might have Rate Types identified as Standard, Holiday, and so on. Each project has a default Rate Type specified.

Tip; The default Rate Type for a project is specified on the Projects > Details > Settings page.

Options for choosing an assignment rate

Every resource and role can have up to five price/unit values specified, corresponding to each of the five Rate Types. If you have the required module access and privileges, you can specify resource and role price/unit values on the Resources > Details > Units & Prices page.

When you assign a resource or role to an activity, the project’s default Rate Type is applied to the assignment and the Rate Source is set to resource or role, as applicable. The price/unit for the assignment is determined based on these two settings.

If you do not want to use the project’s default Rate Type for a specific assignment, you can choose a different Rate Type. If a resource or role does not have a price/unit defined for the Rate Type you select, the project default price/unit is applied to the activity. When the project default price/unit is applied, a caret symbol (^) appears in the Price/Unit field on the Activity Resource Details page.

Additionally, if an assignment has both a resource and a role designated, you can use the Rate Source field to specify whether you want to use the rate for the resource or the role. If you want to record a specific price/unit for an assignment instead of applying the rate for resource or role, you can use the Rate Source field Override option.

So that is all about How to Determine Resource Rate in Primavera P6. We think that it is good information about How to Determine Resource Rate in Primavera P6. We hope that this information is useful for you. Please share if you think that this information can be useful for others. If you need more article related to How to Determine Resource Rate in Primavera P6 you can simply subscribe this blog. Thanks for visiting and have a nice browsing. source: oracle.com