How to Reduce Total Float in Primavera P6? This article is about How to Reduce Total Float in Primavera P6. In this article we are trying to provide you good information about How to Change Total Float in Primavera P6. We have arranged the information in this post to make you understand it easily. We hope that you can understand it well. Please check the information below.

How to Reduce Total Float in Primavera P6

How to Reduce Total Float in Primavera P6

One of the ways Primavera’s project-planning software calculates project duration is with Total Float. At the most basic level, Total Float displays the difference between the start and end times. However, there is more fluctuation than that might imply. To reduce Total Float while keeping the same start and end deadlines, you can modify Total Float options. There are three ways to calculate Total Float, some of which will be smaller than others.

Sponsored Links :

Open your project in Primavera P6.

Select “Schedule” from the “Tools” menu.

Click “Options,” and then the “General” tab.

Choose a new selection under “Calculate total float as.” The options are “Most critical,” “Start float” and “Finish float.” For most projects “Most critical” would give you the smallest float, since it only includes the phase(s) of the project you have marked as critical.

Click “OK” to save the Total Float information.

So that is all about How to Reduce Total Float in Primavera P6. We think that it is good information about How to Reduce Total Float in Primavera P6. We hope that this information is useful for you. Please share this article to your community if you think that this information can be useful for others. If you need more article related to How to change Total Float in Primavera P6 you can simply subscribe this blog. Thanks for visiting and have a nice browsing. source: Project Planning and Scheduling Using Primavera P6